Issues Found — Review Recommended
Sample report — example project, details anonymized.

[ANONYMIZED] Single-Family Residence — New Smyrna Beach, FL — Review Complete

Plan Review Report — August 15, 2026

Get your own review free — 3 reviews, no credit card
72Score

Needs Work

The plan set is generally complete but needs work before submission.

The cover sheet is missing the required wind-speed and exposure notations, which is a common cause of first-round comments in Volusia County.

The site plan shows the correct setbacks, but the flood vent detail on the elevation drawings does not match the noted BFE.

The floor plans and structural sheets are in good shape — the foundation plan, framing, and shear wall schedules are all present and consistent.

4 Flagged3 Advisory6 Passed
Reviewed against: 2023 FBC, 8th Edition · New Smyrna Beach, Volusia County, FL · Wind Zone: Wind-Borne Debris Region

Project type

New Construction — Single-Family Residence

Address

[ANONYMIZED ADDRESS], New Smyrna Beach, FL

Stories

2 Stories

Square footage

2,840 sq ft

Design wind speed

150 mph (Ultimate)

Electrical code

2023 NEC (FBC 8th Ed.)

The cover sheet is mostly complete but is missing the wind-speed and exposure category notations that Volusia County requires on the first sheet. Adding these now avoids a near-certain first-round comment.

Wind-speed and exposure category notations are missing from the cover sheet.

FBC 2023 §1609.1 / R301.2.1major
Sheet A-001 (Cover Sheet)General notes block, upper right

Add the following line to the general notes: "Design Wind Speed: 150 mph (Ultimate), Exposure C, Risk Category II." Place it directly under the project address block.

The project address is listed but the building department permit number placeholder is blank.

FBC 2023 §105.1minor
Sheet A-001 (Cover Sheet)Title block, lower right

Add "Permit No.: __________" to the title block so the reviewer can fill it in at intake.

Setbacks, lot coverage, and impervious area all meet the City of New Smyrna Beach Land Development Code. No action needed here.

Front, side, and rear setbacks (25' / 7.5' / 25') meet RS-1 district minimums.
Lot coverage at 28% is under the 35% maximum for the RS-1 district.

Floor plans are dimensioned consistently and the egress paths are clear. The habitable room minimum areas and ceiling heights all meet code.

All habitable rooms meet the 70 sq ft minimum and 7' minimum horizontal dimension.
Ceiling heights of 8'-0" meet the 7'-0" minimum throughout habitable space.

The foundation plan is complete, but one footing-to-slab connection detail should be clarified before the reviewer asks.

Footing-to-slab connection detail at the garage entry is shown generically and does not call out the dowel size and spacing.

FBC 2023 §R403.1 / R608.6minor
Sheet S-002 (Foundation Details)Detail 4/SD-2

Add the callout "#4 dowels @ 24" O.C. each way" to Detail 4/SD-2 to match the rest of the foundation details.

Framing plans, beam schedules, and joist/rafter sizes are consistent with the span tables and load paths.

LVL beam sizes in the beam schedule match the posted spans and tributary loads.
Joist and rafter spans are within the prescriptive IRC span tables for Southern Pine #2.

Egress doors, exit access travel distances, and emergency escape and rescue openings are all code-compliant.

Each sleeping room has a compliant emergency escape and rescue opening (egress window or door).

The Florida Energy Code compliance path is noted, but the insulation R-values on the details do not match the values stated in the energy compliance form.

Wall cavity insulation R-value on the wall detail (R-13) does not match the R-20 stated on the Energy Code Compliance Form.

FBC 2023 Energy Conservation §402.1major
Sheet A-301 (Wall Details) vs Form R405-1Wall Section 2 / A-301

Update the wall detail to show "R-20 batt + R-5 continuous insulation" to match the energy compliance form, or revise the form to reflect the actual assembly.

MEP layouts are standard and complete. One equipment location note is worth tightening up.

The condenser location is shown but the required clearance from the property line is not dimensioned.

FBC 2023 §M1401 / NEC 110.26minor
Sheet M-001 (Mechanical Plan)Condenser pad, northeast elevation

Add a dimension showing at least 3' clearance from the property line to the condenser, per the manufacturer's minimum clearance.

This is the section most likely to cause a resubmittal in Volusia County. The wind-borne debris region requirements are present but the impact-rated opening schedule is incomplete.

Impact-rated opening schedule does not list product approval numbers for the garage door.

FBC 2023 §R301.2.1.2 / TAS-201major
Sheet S-004 (Opening Schedule)Opening Schedule, row 4

Add the Florida Product Approval number (e.g., "FL-XXXX") and the ASTM E1996 large-missile rating for the garage door to the opening schedule.

Roof-to-wall connection tie-down strap is called out but the strap capacity is not stated.

FBC 2023 §R802.11 / §1604.4major
Sheet S-003 (Framing Plan)Section 1/SD-3, perimeter wall

Add the strap uplift capacity (e.g., "H10A — 1,135 lb uplift") to the framing detail and verify it against the calculated uplift load.

The property is in a FEMA AE flood zone. The BFE is noted, but the flood vent detail on the elevation drawings does not match the required venting area.

Flood vent opening area shown on the elevation detail (1 sq ft) does not meet the 1 sq ft per 1 sq ft of enclosed area rule for the crawlspace.

FBC 2023 §R322 / ASCE 24major
Sheet A-401 (Elevations) vs Sheet S-002North Elevation, vent notation

Add a second flood vent to the opposite elevation to reach the total required venting area (2 sq ft for this crawlspace), and label each "Engineered Flood Vent — rated for 1 sq ft of venting."

Get your own review free — 3 reviews, no credit card

This is an anonymized example. Your real report will reference your project name, jurisdiction, and plan sheets.